Construction update October 2025
Update about construction of Westside Community Church building.
Current things
Update as of 10/14//2025
Site: Site work is nearing completion. Grade work is complete with the first layer of stone. Water lines will be completed soon. The septic field has been installed, and the tanks and lift station will be installed once the building foundation is complete.
Building: We received the building permit to allow construction to begin. Rebar arrived this week, and we’re awaiting mobilization of the concrete contractor. The steel structure is scheduled for delivery around Thanksgiving. The building team continues to work on interior details, product selections, and vendor pricing. We anticipate starting building erection before Christmas.
Action Items for the Church:
God has been working through all of this in His own way and timing, and we continue to see His hand in this.
1. Pray that the church body stays united in this effort and to align with God's desire to grow His kingdom in the community around us. Acts 5:39
2. Pray that God's will be done, on earth as it is in heaven. Matthew 6:10
3. Pray for the building team, the finance team, the elders, and the church staff to lead humbly and serve God faithfully. Philippians 2:1-5; 2 Timothy 2
4. Pray about your own effort for the building project. There will be a large effort needed for volunteer work during the construction phase, and we must prepare our hearts for the service ahead. Matthew 9:37-38; Nehemiah 3